Dojo · Finding · Then and now · as of

Tesla Dojo supercomputer: then vs now

Share on XDownload imageShare timeline

Proposition (held fixed): Would Tesla’s own Dojo training supercomputer become world-class, and when would Dojo 1 and Dojo 2 be online at volume? This page tracks dated Elon wording on Dojo. It is not a chip-benchmark page.

2022Dojo “operational next year”, as dated in 2021
end of 2025Dojo 2 in volume, as dated in 2024
10 Aug 2025Elon: shut down Dojo
Then vs now · Tesla Dojo

From a custom training computer aiming to be the best in the world, to one chip roadmap where “all paths converged to AI6”.

Then · 20 Sep 2020 · X reply

“Dojo uses our own chips & a computer architecture optimized for neural net training, not a GPU cluster. Could be wrong, but I think it will be best in world.”

Latest · current statusNow · 14 Nov 2025 · Baron Investment Conference 2025

“And then, we also had the Dojo program, which was doing it was also doing okay, but but not on a path to be competitive with Nvidia. So, I I collapsed the I collapsed the two programs into just one program just to get everyone focused on AI 5 chip, which is essential.”

Aug 2021: “So we should have Dojo operational next year” 19 Aug 2021 · Tesla AI Day 2021 · 2:16:21
Sep 2024: “we should have Dojo 2 in volume towards the end of next year” 9 Sep 2024 · All-In Summit 2024 · 45:45
Jun 2025: “Dojo 2 is good, but Dojo 3 will be great.” 5 Jun 2025 · X post
Aug 2025: “Once it became clear that all paths converged to AI6, I had to shut down Dojo and make some tough personnel choices, as Dojo 2 was now an evolutionary dead end. Dojo 3 arguably lives on in the form of a large number of AI6 SoCs on a single board.” 10 Aug 2025 · X reply
What did not change: Tesla still designs its own inference silicon · training still needs a lot of compute · Elon still frames custom silicon as a path around buying every GPU.
ElonsFAQ corpus · verified 2026-10-23 · unofficial.
Share on XDownload image
Dojo: from “best in world” to one chip roadmap built on AI5 and AI6Timeline of Elon Musk statements on Tesla Dojo: still being built, maybe a year from V1.0 (August 2020); could be best in world (September 2020); operational next year (August 2021); phase in, fewer incremental GPUs next year (August 2022); biggest architecture overhaul since Cray (July 2023); Dojo 1 about 8k H100-equivalent by end of 2024 and double down versus Nvidia (July 2024); Dojo 2 in volume toward the end of 2025 (September 2024); Dojo 1 active, Dojo 2 about 10 times better (March 2025); Dojo 2 later this year, Dojo 3 will be great (June 2025); shut down Dojo, Dojo 2 an evolutionary dead end (August 2025); collapsed the programs onto the AI5 chip (November 2025).THEN AND NOW · TESLA DOJODojo: from “best in world” to one chip roadmap built on AI5 and AI6Aug 2020: V1.0 in about a year → Sep 2020: “best in world” → Aug 2021: operational next year → Jul 2024: double down, ~8k H100-eq by year end → Sep 2024: Dojo 2 in volume end of 2025 → Jun 2025: Dojo 2 later this year, Dojo 3 will be great → Aug 2025: shut down, Dojo 2 a dead end → Nov 2025: collapsed into AI5.20202021202220232024202520262027as of 1234567891011claim with a daterestated / revisedobserved statusstatement → stated target date115 Aug 2020X reply“Dojo is still being built. Maybe a year or so from V1.0.”TARGET 2021 · V1.0220 Sep 2020X reply“Could be wrong, but I think it will be best in world.”TARGET best in world319 Aug 2021Tesla AI Day 2021 · 2:16:21“So we should have Dojo operational next year”TARGET 2022 · operational413 Aug 2022X reply“We’ll phase in Dojo. Won’t need to buy as many incremental GPUs next year.”TARGET 2023 · phase in523 Jul 2023X reply“Dojo is arguably the biggest computer architecture overhaul since Cray.”TARGET architecture overhaul623 Jul 2024X reply“And Dojo 1 will have roughly 8k H100-equivalent of training online by end of year. … we are going to double down on Dojo”TARGET end of 2024 · ~8k H100-eq79 Sep 2024All-In Summit 2024 · 45:45“we should have Dojo 2 in volume towards the end of next year”TARGET end of 2025 · Dojo 2 volume820 Mar 2025Tesla All-Hands (Q1 2025) · 25:16“So we've got Dojo 1 active now in Gigafactory New York and in Palo Alto. … Dojo 2 that's coming down the line that'll be probably 10 times better”TARGET Dojo 1 active · Dojo 2 10×95 Jun 2025X post“We start bringing Dojo 2 online later this year. … Dojo 2 is good, but Dojo 3 will be great.”TARGET later 2025 · Dojo 21010 Aug 2025X reply“I had to shut down Dojo … as Dojo 2 was now an evolutionary dead end.”TARGET status: shut down1114 Nov 2025Baron Investment Conference 2025 · 47:30“not on a path to be competitive with Nvidia. … I collapsed the two programs into just one program”TARGET status: collapsed into AI5LATEST · NOWelonsfaq.org · sources: @elonmusk on X, Tesla AI Day 2021, Tesla Q2 2024 call, All-In Summit 2024, Tesla All-Hands Mar 2025, Baron 2025 · as of 29 Oct 2026 · unofficialDojo: from “best in world” to one chip roadmap built on AI5 and AI6Timeline of Elon Musk statements on Tesla Dojo: still being built, maybe a year from V1.0 (August 2020); could be best in world (September 2020); operational next year (August 2021); phase in, fewer incremental GPUs next year (August 2022); biggest architecture overhaul since Cray (July 2023); Dojo 1 about 8k H100-equivalent by end of 2024 and double down versus Nvidia (July 2024); Dojo 2 in volume toward the end of 2025 (September 2024); Dojo 1 active, Dojo 2 about 10 times better (March 2025); Dojo 2 later this year, Dojo 3 will be great (June 2025); shut down Dojo, Dojo 2 an evolutionary dead end (August 2025); collapsed the programs onto the AI5 chip (November 2025).THEN AND NOW · TESLA DOJODojo: from “best in world” to one chip roadmap built on AI5 and AI6Aug 2020: V1.0 in about a year → Sep 2020: “best in world” → Aug 2021: operational next year → Jul 2024: double down, ~8k H100-eq by year end → Sep 2024: Dojo 2 in volume end of 2025 → Jun 2025: Dojo 2 later this year, Dojo 3 will be great → Aug 2025: shut down, Dojo 2 a dead end → Nov 2025: collapsed into AI5.20202021202220232024202520262027as of 1234567891011claim with a daterestated / revisedobserved statusstatement → stated target date115 Aug 2020X reply“Dojo is still being built. Maybe a year or so from V1.0.”TARGET 2021 · V1.0220 Sep 2020X reply“Could be wrong, but I think it will be best in world.”TARGET best in world319 Aug 2021Tesla AI Day 2021 · 2:16:21“So we should have Dojo operational next year”TARGET 2022 · operational413 Aug 2022X reply“We’ll phase in Dojo. Won’t need to buy as many incremental GPUs next year.”TARGET 2023 · phase in523 Jul 2023X reply“Dojo is arguably the biggest computer architecture overhaul since Cray.”TARGET architecture overhaul623 Jul 2024X reply“And Dojo 1 will have roughly 8k H100-equivalent of training online by end of year. … we are going to double down on Dojo”TARGET end of 2024 · ~8k H100-eq79 Sep 2024All-In Summit 2024 · 45:45“we should have Dojo 2 in volume towards the end of next year”TARGET end of 2025 · Dojo 2 volume820 Mar 2025Tesla All-Hands (Q1 2025) · 25:16“So we've got Dojo 1 active now in Gigafactory New York and in Palo Alto. … Dojo 2 that's coming down the line that'll be probably 10 times better”TARGET Dojo 1 active · Dojo 2 10×95 Jun 2025X post“We start bringing Dojo 2 online later this year. … Dojo 2 is good, but Dojo 3 will be great.”TARGET later 2025 · Dojo 21010 Aug 2025X reply“I had to shut down Dojo … as Dojo 2 was now an evolutionary dead end.”TARGET status: shut down1114 Nov 2025Baron Investment Conference 2025 · 47:30“not on a path to be competitive with Nvidia. … I collapsed the two programs into just one program”TARGET status: collapsed into AI5LATEST · NOWelonsfaq.org · sources: @elonmusk on X, Tesla AI Day 2021, Tesla Q2 2024 call, All-In Summit 2024, Tesla All-Hands Mar 2025, Baron 2025 · as of · unofficial

Dojo: from “best in world” to one chip roadmap built on AI5 and AI6

Aug 2020: V1.0 in about a year → Sep 2020: “best in world” → Aug 2021: operational next year → Jul 2024: double down, ~8k H100-eq by year end → Sep 2024: Dojo 2 in volume end of 2025 → Jun 2025: Dojo 2 later this year, Dojo 3 will be great → Aug 2025: shut down, Dojo 2 a dead end → Nov 2025: collapsed into AI5.

  • claim with a date
  • restated / revised
  • observed status
  1. 15 Aug 2020X reply“Dojo is still being built. Maybe a year or so from V1.0.”Target: 2021 · V1.0
  2. 20 Sep 2020X reply“Could be wrong, but I think it will be best in world.”Target: best in world
  3. 19 Aug 2021Tesla AI Day 2021 · 2:16:21“So we should have Dojo operational next year”Target: 2022 · operational
  4. 13 Aug 2022X reply“We’ll phase in Dojo. Won’t need to buy as many incremental GPUs next year.”Target: 2023 · phase in
  5. 23 Jul 2023X reply“Dojo is arguably the biggest computer architecture overhaul since Cray.”Target: architecture overhaul
  6. 23 Jul 2024X reply“And Dojo 1 will have roughly 8k H100-equivalent of training online by end of year. … we are going to double down on Dojo”Target: end of 2024 · ~8k H100-eq
  7. 9 Sep 2024All-In Summit 2024 · 45:45“we should have Dojo 2 in volume towards the end of next year”Target: end of 2025 · Dojo 2 volume
  8. 20 Mar 2025Tesla All-Hands (Q1 2025) · 25:16“So we've got Dojo 1 active now in Gigafactory New York and in Palo Alto. … Dojo 2 that's coming down the line that'll be probably 10 times better”Target: Dojo 1 active · Dojo 2 10×
  9. 5 Jun 2025X post“We start bringing Dojo 2 online later this year. … Dojo 2 is good, but Dojo 3 will be great.”Target: later 2025 · Dojo 2
  10. 10 Aug 2025X reply“I had to shut down Dojo … as Dojo 2 was now an evolutionary dead end.”Target: status: shut down
  11. 14 Nov 2025Baron Investment Conference 2025 · 47:30“not on a path to be competitive with Nvidia. … I collapsed the two programs into just one program”Target: status: collapsed into AI5
Share this timelineShare timelineDownload timeline imageTall version

Then

15 August 2020, on X:

“Dojo is still being built. Maybe a year or so from V1.0.”

20 September 2020, on X:

“Dojo uses our own chips & a computer architecture optimized for neural net training, not a GPU cluster. Could be wrong, but I think it will be best in world.”

19 August 2021, Tesla AI Day:

“So we should have Dojo operational next year”

Editorial calendar reading: “next year” from Aug 2021 = 2022.

13 August 2022, on X:

“We’ll phase in Dojo. Won’t need to buy as many incremental GPUs next year.”

23 July 2023, on X:

“Dojo is arguably the biggest computer architecture overhaul since Cray. Doesn’t mean it succeeds, but it doesn’t lack for boldness.”

23 July 2024, on X and on the Tesla Q2 2024 earnings call:

“And Dojo 1 will have roughly 8k H100-equivalent of training online by end of year. Not massive, but not trivial either.”
“So we are going to double down on Dojo and we do see a path to being competitive with Nvidia with, with Dojo.”

9 September 2024, All-In Summit:

“we should have Dojo 2 in volume towards the end of next year”

Editorial calendar reading: “the end of next year” from Sep 2024 = end of 2025.

20 March 2025, Tesla all-hands:

“So we've got Dojo 1 active now in Gigafactory New York and in Palo Alto.”
“And then we've got Dojo 2 that's coming down the line that'll be probably 10 times better than Dojo 1.”

5 June 2025, on X:

“Tesla Dojo AI training computer making progress. We start bringing Dojo 2 online later this year. It takes three major iterations for a new technology to be great. Dojo 2 is good, but Dojo 3 will be great.”

Now

10 August 2025, on X:

“Once it became clear that all paths converged to AI6, I had to shut down Dojo and make some tough personnel choices, as Dojo 2 was now an evolutionary dead end. Dojo 3 arguably lives on in the form of a large number of AI6 SoCs on a single board.”

14 November 2025, Baron Investment Conference, looking back at the chip programs:

“And then, we also had the Dojo program, which was doing it was also doing okay, but but not on a path to be competitive with Nvidia. So, I I collapsed the I collapsed the two programs into just one program just to get everyone focused on AI 5 chip, which is essential.”

What changed

ItemThen (2020–mid 2025)Now (from 10 Aug 2025)
Statuscustom training computer, Dojo 1 online, Dojo 2 “later this year” / in volume end of 2025shut down; Dojo 2 called an evolutionary dead end
Ambition“best in world”; competitive with Nvidia; Dojo 3 “will be great”collapsed onto AI5 inference silicon; Dojo 3 “arguably lives on” as AI6 SoCs on a board
Whyown chips so Tesla would not have to buy as many incremental GPUs“all paths converged to AI6”

What did not change

Neutral conclusion

From 2020 through June 2025 Elon described Dojo as Tesla’s own training supercomputer: maybe a year from V1.0, possibly best in the world, operational the next year, then Dojo 1 on the order of 8,000 H100-equivalents by the end of 2024, with Dojo 2 in volume toward the end of 2025 and Dojo 3 to follow. On 10 August 2025 he wrote that he had shut Dojo down because Dojo 2 was an evolutionary dead end once paths converged on AI6. In November 2025 he said the Dojo program had not been on a path to compete with Nvidia and that he had collapsed the two chip programs onto AI5. This compares dated wording; it makes no claim about motives or whether AI6 replaced the same workload.

Scope